= StarForth C↔Isabelle Refinement Implementation Roadmap
|
||
:toc: left
|
||
:toclevels: 2
|
||
:sectnums:
|
||
:source-highlighter: rouge
|
||
:icons: font
|
||
|
||
== Executive Summary
|
||
|
||
This roadmap establishes the phased approach to proving that the StarForth C implementation correctly refines the Isabelle formal specifications.
|
||
|
||
**Overall Goal:** Complete end-to-end refinement verification of running code against theory.
|
||
|
||
**Timeline:** 6-8 months (estimated, aggressive schedule)
|
||
|
||
**Success Criteria:** All critical VM functions have complete refinement proofs with no remaining `sorry`s.
|
||
|
||
---
|
||
|
||
== Vision & Philosophy
|
||
|
||
**What we're building:** A proof system that ensures the C implementation:
|
||
1. Implements exactly what the theory specifies 2. Maintains all proven invariants 3. Handles all edge cases correctly
|
||
|
||
**Our approach:**
|
||
- Iterative: Find discrepancies → Fix theory or code → Prove → Repeat - Transparent: Every defect logged, tracked, and explained - Pragmatic: Start with core VM, expand systematically - Auditor-friendly: All documentation publically reviewable
|
||
|
||
---
|
||
|
||
## Phase 1: VM Core Refinement
|
||
|
||
**Duration:** 4-6 weeks
|
||
**Effort:** ~320 developer-hours
|
||
**Team:** 2-3 (1 Isabelle specialist, 1-2 C developers)
|
||
|
||
### Scope
|
||
|
||
Prove that `src/vm.c` correctly implements:
|
||
- Stack operations (push, pop, overflow handling) - Return stack operations (CALL, RET) - Instruction dispatch mechanism - Program counter management - Error state consistency
|
||
|
||
### Deliverables
|
||
|
||
1. **Annotated source** - All vm.c functions have REFINEMENT headers
|
||
2. **Proof file** - `StarForth_Refinement.thy` with lemmas for each function
|
||
3. **CAPA updates** - All 3 initial defects (DEFECT-001, 002, 003) resolved
|
||
4. **Tests** - Unit tests verifying stack invariants under all conditions
|
||
|
||
### Key Functions to Refine
|
||
|
||
[cols="1,2,2,1"]
|
||
|===
|
||
| Function | Theory | Est. Hours | Status
|
||
|
||
| `stack_push()` | `VM_Stacks.thy::push` | 20 | OPEN
|
||
| `stack_pop()` | `VM_Stacks.thy::pop` | 20 | OPEN
|
||
| `execute_call()` | `VM_Stacks.thy::call` | 25 | OPEN
|
||
| `execute_return()` | `VM_Stacks.thy::ret` | 25 | OPEN
|
||
| `execute_instruction()` | `VM_Core.thy::exec_instr` | 60 | OPEN
|
||
| `dispatch_* helpers` | VM_*_Words.thy | 80 | OPEN
|
||
| Stack invariants (proofs) | VM_StackRuntime.thy | 50 | OPEN
|
||
|===
|
||
|
||
### Success Criteria
|
||
|
||
- ✅ No remaining `sorry` statements in refinement proofs
|
||
- ✅ All stack bounds violations caught and proven impossible
|
||
- ✅ All error paths formally verified
|
||
- ✅ All tests pass without instrumentation
|
||
- ✅ DEFECT log shows 0 OPEN items for Phase 1
|
||
|
||
### Risks
|
||
|
||
**High Risk:**
|
||
- Pre/post-increment semantics mismatch (mitigated by careful lemmas)
|
||
|
||
**Medium Risk:**
|
||
- Error handling complexity (plan: explicit state modeling)
|
||
|
||
**Low Risk:**
|
||
- Stack size assumptions (clearly specified and checked)
|
||
|
||
### Dependencies
|
||
|
||
- Isabelle/HOL installed and working
|
||
- Existing VM_Stacks.thy theory complete
|
||
- C code has no undefined behavior (must audit first)
|
||
|
||
### Successor
|
||
|
||
Cannot proceed to Phase 2 until Phase 1 complete.
|
||
|
||
---
|
||
|
||
## Phase 2: Utility Functions & Memory Management
|
||
|
||
**Duration:** 2-3 weeks
|
||
**Effort:** ~160 developer-hours
|
||
**Team:** 1-2
|
||
|
||
### Scope
|
||
|
||
Prove correctness of:
|
||
- Memory allocation/deallocation patterns - Initialization sequences - Resource cleanup - Error recovery (if applicable) - All root-level .c files
|
||
|
||
### Deliverables
|
||
|
||
1. Memory model formalization in Isabelle
|
||
2. Proof that allocations don't exceed bounds
|
||
3. Proof that cleanup prevents leaks
|
||
4. Updated CAPA log
|
||
|
||
### Success Criteria
|
||
|
||
- ✅ All OPEN defects resolved
|
||
- ✅ Memory model and C code proven equivalent
|
||
- ✅ No unsafe patterns in utility code
|
||
|
||
### Dependencies
|
||
|
||
- Phase 1 complete
|
||
|
||
---
|
||
|
||
## Phase 3: Test Harness Integration
|
||
|
||
**Duration:** 1-2 weeks
|
||
**Effort:** ~80 developer-hours
|
||
**Team:** 1
|
||
|
||
### Scope
|
||
|
||
Prove that the test framework validates theory-level properties:
|
||
- Test assertions map to Isabelle lemmas - Test execution traces provable execution paths - Test coverage covers all critical theory cases
|
||
|
||
### Deliverables
|
||
|
||
1. Test-to-theory mapping document
|
||
2. Isabelle theorems for key test properties
|
||
3. Coverage report linking tests to theory
|
||
|
||
### Success Criteria
|
||
|
||
- ✅ Every critical theory property has a test
|
||
- ✅ Tests and proofs are consistent
|
||
- ✅ Test suite achieves >95% branch coverage
|
||
|
||
### Dependencies
|
||
|
||
- Phase 1 complete
|
||
|
||
---
|
||
|
||
## Phase 4: Primitive Dictionary (Forth Words)
|
||
|
||
**Duration:** 6-8 weeks
|
||
**Effort:** ~320 developer-hours
|
||
**Team:** 2-3
|
||
|
||
### Scope
|
||
|
||
**LARGEST PHASE** - Systematically prove every Forth word:
|
||
|
||
- Arithmetic: `+`, `-`, `*`, `/`, `MOD`, `ABS`, etc.
|
||
- Logic: `AND`, `OR`, `XOR`, `NOT`, etc.
|
||
- Stack: `DUP`, `DROP`, `SWAP`, `ROT`, `PICK`, `ROLL`
|
||
- Memory: `@`, `!`, `C@`, `C!`
|
||
- Control: `IF`, `ELSE`, `BEGIN`, `UNTIL`, `DO`, `LOOP`
|
||
- I/O: `EMIT`, `KEY`, `.` (print)
|
||
- Physics: Custom words in Physics_Formal.thy
|
||
|
||
### Approach
|
||
|
||
**Batch-wise delivery:**
|
||
|
||
**Batch 4.1 (Weeks 1-2):** Core arithmetic & stack ops - Most fundamental, highest ROI - ~40% of typical Forth programs
|
||
|
||
**Batch 4.2 (Weeks 3-4):** Memory operations - Required for data structures - Higher complexity (address space reasoning)
|
||
|
||
**Batch 4.3 (Weeks 5-6):** Control flow - Most complex (loop invariants) - Highest proof difficulty
|
||
|
||
**Batch 4.4 (Weeks 7-8):** I/O & domain-specific words - External effects (harder to formalize) - Physics-specific operations
|
||
|
||
### Deliverables Per Batch
|
||
|
||
- Annotated C implementation
|
||
- Isabelle refinement lemmas
|
||
- Property tests
|
||
- CAPA updates
|
||
|
||
### Success Criteria (Overall)
|
||
|
||
- ✅ All ~200 Forth words have refinement proofs
|
||
- ✅ No sorry's in refinement layer
|
||
- ✅ All definitions reach theory equivalence
|
||
|
||
### Complexity Estimate
|
||
|
||
- **Simple words** (DUP, DROP): 2-4 hours each
|
||
- **Medium words** (arithmetic): 4-8 hours each
|
||
- **Complex words** (control flow): 12-24 hours each
|
||
- **Average across all:** ~4 hours per word × 200 = 800 hours
|
||
- **Parallelizable:** Can split by category (arith, logic, stack, control)
|
||
|
||
### Dependencies
|
||
|
||
- Phase 1 complete
|
||
- Primitive word implementations in C complete/frozen
|
||
|
||
---
|
||
|
||
## Phase 5: VM Expansion & Iteration
|
||
|
||
**Duration:** Ongoing
|
||
**Effort:** ~40 hours per feature
|
||
**Team:** 1+ per new feature
|
||
|
||
### Scope
|
||
|
||
When adding new features to the VM:
|
||
1. Add theory definitions first (or in parallel) 2. Implement C code 3. Write annotated code with REFINEMENT headers 4. Prove refinement before merge 5. Update REFINEMENT_CAPA.adoc
|
||
|
||
### Workflow
|
||
|
||
```
|
||
New Feature Request
|
||
↓
|
||
Update theory (VM_*.thy)
|
||
↓
|
||
Implement C code
|
||
↓
|
||
Annotate with REFINEMENT
|
||
↓
|
||
Write refinement proofs
|
||
↓
|
||
CI: make refinement-phase1/2/3/4/5
|
||
↓
|
||
Tests pass? YES → Merge
|
||
NO → Debug (theory or code)
|
||
```
|
||
|
||
### Success Criteria
|
||
|
||
- ✅ All new features have refinement proofs before merge
|
||
- ✅ No theory-code mismatches introduced
|
||
- ✅ Proof maintenance is integrated into development
|
||
|
||
### Dependencies
|
||
|
||
- All previous phases complete
|
||
- Development team trained on refinement workflow
|
||
|
||
---
|
||
|
||
## Timeline Overview
|
||
|
||
```
|
||
Week 1-2: Phase 1 setup, DEFECT-001, basic stack proofs
|
||
Week 3-6: Phase 1 complete (stack, call/ret, dispatch)
|
||
Week 7-8: Phase 2 (utilities, memory model)
|
||
Week 9: Phase 3 (test integration)
|
||
Week 10-17: Phase 4 (primitives, 4 batches)
|
||
Week 18+: Phase 5 (ongoing, feature expansion)
|
||
|
||
TOTAL: ~6 months to core completion, ~8 months to full dictionary
|
||
```
|
||
|
||
**Gantt Chart:**
|
||
|
||
```
|
||
Phase 1 |████████████████████| (Weeks 1-6)
|
||
Phase 2 |██████████| (Weeks 7-8)
|
||
Phase 3 |██████| (Week 9)
|
||
Phase 4 |████████████████| (Weeks 10-17)
|
||
Phase 5 |→→→→→→→→→ (ongoing)
|
||
```
|
||
|
||
---
|
||
|
||
## Critical Path
|
||
|
||
**Must complete in order:**
|
||
1. Phase 1 ← **BLOCKER for all others**
|
||
2. Phase 2 ← Unlocks complete VM testing 3. Phases 3, 4 ← Can proceed in parallel after Phase 1
|
||
|
||
**CRITICAL DECISION POINTS:**
|
||
|
||
- **End of Phase 1 (Week 6):** Refinement framework working?
|
||
- YES → Proceed to Phase 4 (biggest payoff)
|
||
- NO → Major review needed before continuing
|
||
|
||
- **Mid-Phase 4 (Week 13):** Is proof velocity sustainable?
|
||
- YES → Continue to full dictionary
|
||
- NO → Consider reduced scope (core 50 words only)
|
||
|
||
---
|
||
|
||
## Resource Requirements
|
||
|
||
### Personnel
|
||
|
||
**Mandatory:**
|
||
- 1 Isabelle/HOL expert (40 hrs/week)
|
||
- Proof architecture
|
||
- Lemma design
|
||
- Difficult proof cases
|
||
|
||
- 1-2 C developers (20 hrs/week)
|
||
- Code annotation
|
||
- Refactoring for proofs
|
||
- Test case development
|
||
|
||
**Optional (accelerators):**
|
||
- Second Isabelle specialist (adds 50% velocity, enables parallelism) - Automated proof tool (SMT solvers like Z3, adds 20% velocity)
|
||
|
||
### Tools & Infrastructure
|
||
|
||
Required:
|
||
- Isabelle 2025+ (already have) - Python/Bash for automation - Version control (already have)
|
||
|
||
Optional (nice-to-have):
|
||
- Sledgehammer (proof search) - included with Isabelle - Why3/Frama-C (for enhanced C semantics) - cost: 40 hours setup - Coq (alternative; only if switching frameworks) - not recommended
|
||
|
||
### Compute
|
||
|
||
Modest requirements:
|
||
- Proof checking: < 5 minutes per rebuild - Build machine: 4 cores, 8GB RAM sufficient - Storage: ~2 GB for Isabelle session caches
|
||
|
||
---
|
||
|
||
## Risk Assessment & Mitigation
|
||
|
||
### Risk Matrix
|
||
|
||
[cols="2,2,1,2,2"]
|
||
|===
|
||
| Risk | Probability | Impact | Mitigation | Contingency
|
||
|
||
| Theory spec incomplete | Medium | High | Weekly theory audit | Skip incomplete areas, revisit later
|
||
| C code has subtle bugs | Medium | High | Formal code review | Unit test first, then prove
|
||
| Proofs become intractable | Low | Critical | Research harder lemmas | Simplify spec (less ambitious)
|
||
| Team turnover | Low | Medium | Documentation | Cross-training, recorded sessions
|
||
| Isabelle version issues | Low | Low | Version lock | Pin to Isabelle 2025
|
||
|===
|
||
|
||
### Contingency Plans
|
||
|
||
**If proofs become intractable:**
|
||
1. Reduce scope to core 50 words (high ROI subset) 2. Use `sorry` for complex lemmas, mark as TODO 3. Revisit after proof technique improvements
|
||
|
||
**If Phase 1 extends beyond 6 weeks:**
|
||
1. Allocate +2 people for parallel proofs 2. Drop nice-to-have defects (low severity) 3. Extend timeline, compress Phase 4
|
||
|
||
---
|
||
|
||
## Success Metrics
|
||
|
||
### Phase-by-Phase
|
||
|
||
| Phase | Metric | Target | Method | |-------|--------|--------|--------| | 1 | Proof completeness | 0 `sorry`s | `grep "sorry" *.thy` | | 1 | Defect closure | 100% OPEN→CLOSED | REFINEMENT_CAPA.adoc | | 2 | Memory safety | No leaks | Valgrind + proofs | | 3 | Test coverage | > 95% branch | `gcov` analysis | | 4 | Word coverage | 100% of ~200 | grep word list | | 4 | Proof QC | Zero sorry's | Isabelle build -c |
|
||
|
||
### Overall
|
||
|
||
**HARD STOP CRITERIA (go/no-go):**
|
||
- All Phase 1 proofs compile without `sorry`
|
||
- No bugs found in code by auditors during Phase 1 - Refinement framework proves faster than expected → Accelerate Phase 4
|
||
|
||
**SOFT TARGETS:**
|
||
- 90%+ of dictionary proven by end of Phase 4 - < 1 major theory revision needed during implementation
|
||
|
||
---
|
||
|
||
## How to Use This Roadmap
|
||
|
||
### For Team Members
|
||
|
||
1. **Check current phase:** `make refinement-status`
|
||
2. **See what's blocked:** `grep OPEN docs/REFINEMENT_CAPA.adoc`
|
||
3. **Pick a defect:** Choose smallest OPEN item
|
||
4. **Resolve it:** Follow REFINEMENT_ANNOTATIONS.adoc guide
|
||
5. **Update status:** Edit REFINEMENT_CAPA.adoc, commit
|
||
|
||
### For Project Managers
|
||
|
||
- **Track progress:**
|
||
```bash make refinement-status # Weekly make refinement-report # Monthly ```
|
||
|
||
- **Identify risks:**
|
||
- Is phase extending beyond estimate?
|
||
- Are proof complexity metrics increasing?
|
||
- Is defect resolution rate dropping?
|
||
|
||
- **Make course corrections:**
|
||
- Add specialists if velocity < 3 hours/proof
|
||
- Reduce scope if facing 2+ week delays
|
||
- Consider parallelizing (multiple independent words)
|
||
|
||
### For Auditors
|
||
|
||
1. **Review current status:** `docs/REFINEMENT_CAPA.adoc`
|
||
2. **Examine code:** Look for REFINEMENT: headers in `src/vm.c`
|
||
3. **Check proofs:** `docs/src/internal/formal/StarForth_Refinement.thy`
|
||
4. **Request details:** Link to specific DEFECT entries
|
||
|
||
---
|
||
|
||
## Phase Completion Checklist
|
||
|
||
### Phase 1 Completion Criteria
|
||
|
||
- [ ] All stack operations have complete proofs
|
||
- [ ] All return stack operations have complete proofs
|
||
- [ ] All three defects (DEFECT-001, 002, 003) marked CLOSED
|
||
- [ ] No `sorry` statements remain in refinement proofs
|
||
- [ ] Code review: vm.c passes security/correctness audit
|
||
- [ ] Tests: All stack tests pass with 100% coverage
|
||
- [ ] Documentation: REFINEMENT headers on all functions
|
||
- [ ] Sign-off: Isabelle expert and C lead approve
|
||
|
||
**Readiness for Phase 2:** YES / NO
|
||
|
||
### Phase 2 Completion Criteria
|
||
|
||
- [ ] Memory model formalized
|
||
- [ ] All utility functions annotated
|
||
- [ ] Memory safety properties proven
|
||
- [ ] All OPEN defects for this phase resolved
|
||
- [ ] Code review: Root-level .c files audited
|
||
- [ ] Sign-off: Both C lead and formal methods lead approve
|
||
|
||
**Readiness for Phase 3:** YES / NO
|
||
|
||
### Phase 3 Completion Criteria
|
||
|
||
- [ ] Test-to-theory mapping complete
|
||
- [ ] All critical properties have tests
|
||
- [ ] Test coverage > 95%
|
||
- [ ] Test assertions match lemma postconditions
|
||
- [ ] Sign-off: QA lead and formal methods lead
|
||
|
||
**Readiness for Phase 4:** YES / NO
|
||
|
||
### Phase 4 Completion Criteria
|
||
|
||
- [ ] All ~200 Forth words have refinement proofs
|
||
- [ ] No `sorry` statements in refinement layer
|
||
- [ ] Physics-specific words proven
|
||
- [ ] CAPA log: 0 HIGH severity items open
|
||
- [ ] Code review: All word implementations audited
|
||
- [ ] Batch sign-offs: Each batch formally accepted
|
||
|
||
**Ready for Phase 5 (ongoing):** YES / NO
|
||
|
||
---
|
||
|
||
## Beyond Phase 5: Future Work
|
||
|
||
Once core refinement is complete:
|
||
|
||
1. **Verified compilation** - Use CompCert for C→Assembly with correctness proofs
|
||
2. **Scheduler formalization** - Prove multitasking/concurrency properties
|
||
3. **Performance certification** - Prove complexity bounds on critical paths
|
||
4. **Formal specification of Forth standard** - Align with ISO Forth
|
||
5. **Automated proof generation** - Machine learning for lemma discovery
|
||
|
||
---
|
||
|
||
## Questions & Support
|
||
|
||
**Q: Can we parallelize phases?**
|
||
A: Phase 4 (primitives) can be split into independent proofs.
|
||
Phases 1-3 must be sequential (each is blocker).
|
||
|
||
**Q: What if we find a major bug?**
|
||
A: Log CAPA defect, fix code or theory, continue.
|
||
Bugs found early = cost savings.
|
||
|
||
**Q: How much time should each proof take?**
|
||
A: Simple: 2-4 hrs.
|
||
Medium: 4-12 hrs.
|
||
Complex: 12-24 hrs.
|
||
Average across phase: ~6 hours/function.
|
||
|
||
**Q: Can we use automated tactics?**
|
||
A: Yes!
|
||
Isabelle's Sledgehammer, SMT solvers (Z3, CVC4) highly recommended.
|
||
Reduces manual time by 20-30%.
|
||
|
||
**Q: Should we prove the Forth bootloader too?**
|
||
A: Out of scope for Phase 1-4. Added to Phase 5 as advanced work.
|
||
|
||
---
|
||
|
||
## Version Control
|
||
|
||
This roadmap is maintained in:
|
||
- **File:** `docs/REFINEMENT_ROADMAP.adoc`
|
||
- **Updates:** When phases complete, when risks materialize - **Authority:** Project lead + Formal methods lead
|
||
|
||
**Status:** ACTIVE PLANNING
|
||
**Last Updated:** 2025-10-30
|
||
**Next Review:** End of Phase 1 (Week 6)
|
||
|
||
---
|
||
|
||
## Appendix: Detailed Effort Breakdown
|
||
|
||
### Phase 1 Detailed Estimate (320 hours)
|
||
|
||
| Task | Hours | Notes | |------|-------|-------| | Annotate vm.c | 20 | Add REFINEMENT headers | | Stack ops proofs | 40 | push, pop + invariants | | Call/ret proofs | 50 | Pre/post semantics | | Dispatch refactor | 30 | Make provable | | Dispatch proofs | 60 | Case analysis over opcodes | | Testing/validation | 40 | Unit tests, edge cases | | Bug fixes | 40 | Issues found during proof | | Documentation | 20 | CAPA updates, guides | | **TOTAL** | **320** | ~6 weeks at 2 FTE |
|
||
|
||
### Phase 4 Detailed Estimate (320 hours)
|
||
|
||
| Batch | Words | Hours | Notes | |-------|-------|-------|-------| | 4.1 | DUP, DROP, SWAP, +, -, *, / | 80 | Core ops, straightforward | | 4.2 | @, !, C@, C!, memory ops | 90 | More complex (addresses) | | 4.3 | IF/ELSE/BEGIN/LOOP | 80 | Hardest (invariants) | | 4.4 | I/O, Physics, misc | 70 | Mixed difficulty | | Overhead | Documentation, reviews | 40 | Cross-cutting | | **TOTAL** | **~200 words** | **320** | ~8 weeks at 2 FTE |
|
||
|
||
---
|
||
|
||